Thessaloniki Waste Water Treatment Plant

Thessaloniki Waste Water Treatment Plant

Project Information

Aktor was responsible for the design and construction involving installations and additions to the current facilities.

The works included modifications at the inlet pumping station, replacement of coarse screens, construction of grit removal, construction of intermediate pumping station, bioreactorsand sedimentation tanks, installation of mechanical thickeners, emptying and cleaning of theexisting digesters, construction of rotary thickeners and homogenization tanks, installation of cogeneration engines.

Nowadays, the plant has capacityof300,000 m3/d and treatment capacity of 1,100,000 Population Equivalent.

The wastewater treatment consists of preliminary treatment facilities (coarse and fine screening, grit removal), primary treatment (primary sedimentation), biological wastewater treatment including nitrogen removal, secondary sedimentation, disinfection, sludge treatment facilities (thickening, anaerobic digestion, dewatering) and co-generation plant.

The plant also treats septic sewage.

Aktor is also providing Operation and Maintenance Services for the specific Wastewater Treatment Plant.

The final effluent specifications SS<35mg/l, COD<125mg/l, BOD5<25mg/l, TN<10 mg/l, Total Coliforms <1000 TC/100ml, E-coli Coliforms <200 E-coli/100ml are met.

Thessaloniki Waste Water Treatment Plant
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.

You can adjust all of your cookie settings by navigating the tabs on the left hand side.

For more information on using cookies, click here