New Patras Port

New Patras Port

Project Information

Project: Completion the 1st Phase of Patra port

Construction of Breakwater 840M (by Caisson), completion of quay wall( 200m), construction of new quay wall (200m) and 7.000 m2 of buildings

Completion the 2nd phase of Patra port

 

Marine Works

  • Completion of quay walls 420m , by Concrete Caisson (20,0m X 9,0m X 12,0m )
  • Breakwater 355 by Concrete Caisson (20,0m X 9,0m X 12,0m )
  • Dredging material environmental disposal offshore, 250.000 m3
  • Back filling & Quarry Materials 450.000m3

 

Buildings

  • Central Station & Entrances 6.974 m2

 

Port Land Area (280.000 m2)

  • Asphalt pavements 125.000m2, road network and parking 74.365 m2, sidewalks & concrete pavements 23.200 m2, greens 10.243 m2, Gravel pipe (800mm) 24.195m, Water – Fire – sewage network.

 

Port Facilities:

Bollards, Fenders, Port light Piles, Big Vessel Pillars

 

Completion the 3rd phase of Patra port

 

Marine Works

  • Quay walls 250m , by Concrete Caisson (29,80m X 9,0m X 12,0m ) using AKTOR S.A. owned Caisson Barge
  • Breakwater 210 by Concrete Caisson (29,80m X 9,0m X 12,0m ) using AKTOR S.A. owned Caisson Barge
  • Dredging material environmental disposal offshore,305.000 m3
  • Back filling & Quarry Materials 620.000 m3
  • Drain Pipes 310.000 m
  • Gravel Pipes, D=1.000 mm, (up to -35,0m) 80.000 m

 

Buildings

  • Station & Entrances 5.000 m2

Port Land Area (150.000 m2)

  • Asphalt pavements 100.000m2, road network and parking 60.000 m2, sidewalks & concrete pavements 15.000 m2, greens 6.000 m2, Gravel pipe (800mm) 27.850 m, Water – Fire – sewage network.

Port Facilities:

Bollards, Fenders, Port light Piles, Big Vessel Pillars